Rules for correct application of cementitious floor
The concrete must be dry, solid, free from loose particles, dust, paint, waxes, oils.
Large cavities should be properly addressed before implementation.
After washing well with water and after drying to be primed with the acrylic primer GLX 290, dissolved in a ratio of 3 parts water: 1 part primer.
The absorbent and old surface, are fixed with the same primer.
Apply NSD 600 after the complete drying of the primer (about 2-6 hours).
Drivers must be removed immediately after application.
If conditions causing abrupt drying of the product exist, such as high temperatures, required light spraying with water for the first two days after application.
Allow the product to dry completely before the next application. During the application, but in the next 24 hours, the temperature of the environment and the substrate should be between + 5 ° C and + 35 ° C.

Cementitious

Flooring screeds for all applications either for filling or leveling and suitable for constructions with load problems